Queensland’s new Construction Productivity Code: What principal contractors and subcontractors need to know

Article

4 min. read

|

Key takeaways

The Code applies to Queensland Government-funded construction contracts over $150 million where the tender process starts on or after 17 November 2026.

Principal contractors and subcontractors must give contractual compliance commitments and report unlawful conduct, breaches, disputes and industrial action within 24 hours.

Review contracts, systems and tender commitments now, and settle who escalates and notifies when an issue arises.

The Queensland Construction Productivity Code 2026 (the Code) took effect on 17 November 2026, putting project delivery, workplace practices and accountability firmly on the procurement agenda for government-funded construction.

Queensland’s major projects pipeline has grown to $139.5 billion, creating significant opportunities for the State’s economy, workforce and construction industry over the next five years. Approximately 70 per cent of the funded work comes from the public sector.

The Queensland Government introduced the Code to promote productivity, innovation, effective workplace management and cooperation between project parties. Its goal is to deliver publicly funded projects efficiently, on time and within budget.

For principal contractors (often called head contractors) and subcontractors, the immediate task is to identify which projects are captured and ensure tender commitments can be delivered through contracts, systems and site practices.

The Queensland Procurement Policy 2026 and the Queensland Government Supplier Code of Conduct 2026 continue to apply. This is a good opportunity to review compliance with the QPP and the Supplier Code, as well as the new Code.

What projects does the Code apply to?

The Code applies to Queensland Government-funded construction contracts where:

  • the contract value exceeds $150 million; and
  • the expression of interest or request for tender is issued on or after 17 November 2026.

Smaller projects and existing procurements or contracts may be brought within the Code’s scope through ministerial approval. Existing arrangements are otherwise generally excluded, subject to the detailed transitional provisions.

Privately funded construction work and work carried out by government delivery entities are excluded.

What does the Code require?

For principal contractors

  • Build compliance into contracts and systems: the Code requires enforceable compliance warranties and consent to government compliance inspections, access to relevant records and interviews. Principal contractors must take reasonable steps, within their contractual influence and practical control, to support subcontractor compliance.
  • Actively manage compliance: use all reasonable efforts to ensure subcontractors, consultants and related entities comply with the Code, and actively monitor how they discharge their workplace relations obligations.
  • Prepare and follow a workplace relations management plan: prepare a Workplace Relations Management Plan (WRMP), comply with it, and act consistently with your tender response. The WRMP must cover labour sourcing, workplace arrangements, subcontractor management, industrial relations risks, disputes, site access, productivity and delivery on time and within budget.
  • Report unlawful conduct or breaches quickly: notify the Department of State Development, Infrastructure and Planning (DSDIP) and the client agency within 24 hours of becoming aware of threatened, possible, likely or actual unlawful industrial conduct, or a breach of the Code.
  • Report disputes and project impacts: report industrial relations or work health and safety (WHS) grievances or disputes that may affect costs, other contracts or deadlines within 24 hours. Give regular updates on resolution efforts, establish procedures for early reporting, and accurately record and promptly provide lost-time information.
  • Respond to industrial action: take reasonable steps to resolve industrial action that could affect project delivery, report it within 24 hours, and use all reasonable efforts, including legal remedies where available, to prevent or end unprotected industrial action.
  • Cooperate with compliance checks: give DSDIP access to relevant work, records and people; comply with reasonable access and information requests; and cooperate with investigations.
  • Maintain lawful workplace practices: avoid sham arrangements, unlawful avoidance of obligations, improper right-of-entry arrangements, and workplace arrangements that restrict lawful workforce flexibility or productivity.

For subcontractors

  • Give contractual commitments and access: subcontracts must include a warranty to comply with the Code and must allow DSDIP to inspect relevant work, records and documents, and to interview people where needed to check compliance.
  • Meet legal obligations: comply with applicable laws, court or tribunal orders and industrial instruments. Subcontractors must not use sham contracting; arrangements designed to avoid legal duties or strike-pay obligations; improper right-of-entry arrangements; or practices that undermine freedom of association.
  • Comply with WHS duties: meet all applicable WHS obligations and maintain appropriate safety, risk-management, training, incident-reporting, rehabilitation and record-keeping practices.
  • Follow lawful right-of-entry rules: do not relax or bypass statutory right-of-entry requirements or allow unauthorised people to monitor workplace arrangements.
  • Report unlawful conduct or breaches quickly: notify DSDIP within 24 hours of becoming aware of threatened, possible, likely or actual unlawful industrial conduct, or a breach of the Code.

The Construction Productivity Code 2026 introduces new contractual, compliance and 24-hour reporting obligations for principal contractors and subcontractors on Queensland Government-funded projects over $150 million. Getting these wrong can put tender commitments and future government work at risk, so early advice on your contracts, systems and escalation processes can help you manage issues before they escalate.

We're ready to assist

For further information about the Code or how it may affect your projects please contact our Construction and Major Projects team.
|By Kristen Kipps