|
Payment claims are undoubtedly a quick and effective mechanism of receiving payment when owed, but in the fast-paced world of sending and receiving payment claims, the fundamentals of the Building and Construction Industry Payments Act 2004 (Qld) are often overlooked. The case of Surfabear Pty Ltd v G J Drainage & Concrete Construction Pty Ltd serves as a reminder of how important the fundamentals are.
One of the critical requirements of the Act is identifying the right respondent - you may win at adjudication, but your victory could be short lived. The Surfabear case demonstrates how a Court could intervene and make the decision void.
In this case, Jorgensen, the owner, entered into a residential building contract with a contractor, Surfabear. Certain works, such as excavation works, remained Jorgensen’s responsibility.
Jorgensen engaged GJ Drainage to perform the excavation works. The quotation for the works made no reference to Surfabear. All invoices were sent from GJ Drainage to Jorgensen, who would arrange payment.
During the progress of the contract, changes were made to the excavation plans and GJ Drainage performed additional work.
On 31 August 2008, an invoice was sent from GJ Drainage to Jorgensen for works covered by the quotation plus ‘extra over job’ charges. Jorgensen disputed this amount and made a part payment to cover the works initially contracted for, and additional works undertaken with Jorgensen’s consent. Jorgensen said all other works and charges were unauthorised.
Following this response, GJ Drainage sent a payment claim to Surfabear and proceeded with an adjudication against it. GJ Drainage won at adjudication and filed the adjudication certificate as a judgment.
Surfabear filed an application to have the decision declared void, and to restrain GJ Drainage from taking any steps to enforce the decision. Its reasoning for doing so was that the adjudicator erred in finding that a contract or arrangement existed between itself, Surfabear, and GJ Drainage, as required under the Act. Accordingly, the adjudicator did not have jurisdiction to decide the dispute. GJ Drainage denied this and argued that Surfabear failed to comply with the requirements of the Act when bringing its proceedings.
The judge referred to the Brodyn case, noting that one of the “basic and essential requirements” for a valid adjudicator’s decision is the “existence of a construction contract between the claimant and the respondent, to which the Act applies”.
The key issue to be decided was whether “on the balance of probabilities, no reasonable adjudicator could have been reasonably satisfied that the respondent had satisfied its onus of showing that a construction contract existed as between it and the applicant”.
The judge answered that question in the affirmative, and found that even if arrangements that are not legally binding fall within the definition of construction contract, the “arrangement” in question still needs to be between the parties in dispute, which was not the case in this instance. The judge found that GJ Drainage was “not a party to the building contract, nor did it have any entitlement to payment under the loan agreement”.
He said that at most “there was some loose form of understanding under which the applicant was to pay the respondent,” and the evidence was “equivocal and cannot support the finding” against Surfabear.
What does this mean for you?
Claimants
Serving the correct entity is critical. To make sure you know who this is, you should always ensure that you have a written agreement for any works performed, clearly naming the parties and executed by the parties.
Respondents
If you have an adjudication decision made against you where you are not a party to the contract, all is not lost. You may have the right to have the decision declared void, preventing an unfair enforcement against you.
Please click on the PDF link to download a full copy of this newsletter.
|